SOLUTION | AMS | TMS | APD | DPD | METHOD | TYPE | EF | CT | EXP | DL |
---|---|---|---|---|---|---|---|---|---|---|
Technische Logistik - 2017-12-22 | 153.4 | 187 | 97.5 | 27.8139 | WPR_GA | D | 1000 | 0 | n/a |
|
Comment by author: Objective Single-MS |
PROJECT | CPD | MS | SD | PD | RG | CPD & MS | DOWNLOAD | |
---|---|---|---|---|---|---|---|---|
Project 1 | 44 | 94 | 0 | 50 | 113.64 % |
|
||
Project 2 | 62 | 184 | 0 | 122 | 196.77 % |
|
||
Project 3 | 59 | 179 | 1 | 120 | 203.39 % |
|
||
Project 4 | 50 | 168 | 0 | 118 | 236.00 % |
|
||
Project 5 | 53 | 173 | 0 | 120 | 226.42 % |
|
||
Project 6 | 56 | 170 | 0 | 114 | 203.57 % |
|
||
Project 7 | 56 | 160 | 0 | 104 | 185.71 % |
|
||
Project 8 | 57 | 155 | 0 | 98 | 171.93 % |
|
||
Project 9 | 65 | 120 | 0 | 55 | 84.62 % |
|
||
Project 10 | 57 | 131 | 0 | 74 | 129.83 % |
|