Login E-Mail: Password: Forgot your Password? Register  
 Ranking & Analysis > Problem: mp_j120_a20_nr5_AgentCopp5 > Solution: 3895
.: Analysis   < previous  next >
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-24 255.3 351 156.55 73.0259 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 85 119 0 34 40.00 %
 Project 2 71 116 0 45 63.38 %
 Project 3 114 340 0 226 198.25 %
 Project 4 116 344 0 228 196.55 %
 Project 5 105 327 0 222 211.43 %
 Project 6 102 162 0 60 58.82 %
 Project 7 102 141 0 39 38.24 %
 Project 8 94 141 0 47 50.00 %
 Project 9 97 208 0 111 114.43 %
 Project 10 102 236 0 134 131.37 %
 Project 11 101 247 0 146 144.55 %
 Project 12 117 313 0 196 167.52 %
 Project 13 96 281 0 185 192.71 %
 Project 14 119 306 0 187 157.14 %
 Project 15 92 299 1 207 225.00 %
 Project 16 92 310 5 218 236.96 %
 Project 17 98 307 2 209 213.27 %
 Project 18 90 310 3 220 244.44 %
 Project 19 81 293 6 212 261.73 %
 Project 20 101 306 1 205 202.97 %