.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-24 218.45 326 123 57.78 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 94 147 0 53 56.38 %
 Project 2 85 112 0 27 31.76 %
 Project 3 70 112 0 42 60.00 %
 Project 4 83 273 0 190 228.92 %
 Project 5 72 257 0 185 256.94 %
 Project 6 105 235 0 130 123.81 %
 Project 7 91 278 0 187 205.49 %
 Project 8 107 277 0 170 158.88 %
 Project 9 87 146 0 59 67.82 %
 Project 10 99 264 0 165 166.67 %
 Project 11 97 275 0 178 183.51 %
 Project 12 103 163 0 60 58.25 %
 Project 13 119 192 2 73 61.34 %
 Project 14 101 163 0 62 61.39 %
 Project 15 96 206 2 110 114.58 %
 Project 16 93 205 1 112 120.43 %
 Project 17 112 240 2 128 114.29 %
 Project 18 110 286 5 176 160.00 %
 Project 19 84 269 1 185 220.24 %
 Project 20 101 269 1 168 166.34 %