.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-24 223.75 314 128.3 53.9738 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 94 158 0 64 68.09 %
 Project 2 85 127 0 42 49.41 %
 Project 3 70 145 0 75 107.14 %
 Project 4 83 234 0 151 181.93 %
 Project 5 72 263 0 191 265.28 %
 Project 6 105 293 0 188 179.05 %
 Project 7 91 279 0 188 206.59 %
 Project 8 107 287 0 180 168.22 %
 Project 9 87 179 0 92 105.75 %
 Project 10 99 276 0 177 178.79 %
 Project 11 97 285 0 188 193.81 %
 Project 12 103 171 0 68 66.02 %
 Project 13 119 186 2 67 56.30 %
 Project 14 101 149 0 48 47.52 %
 Project 15 96 232 9 136 141.67 %
 Project 16 93 194 1 101 108.60 %
 Project 17 112 228 2 116 103.57 %
 Project 18 110 260 4 150 136.36 %
 Project 19 84 269 0 185 220.24 %
 Project 20 101 260 4 159 157.43 %