.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-24 137.6 193 38.8 24.8676 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 85 110 0 25 29.41 %
 Project 2 71 86 0 15 21.13 %
 Project 3 114 180 0 66 57.89 %
 Project 4 116 193 0 77 66.38 %
 Project 5 105 181 0 76 72.38 %
 Project 6 102 122 0 20 19.61 %
 Project 7 102 120 0 18 17.65 %
 Project 8 94 113 0 19 20.21 %
 Project 9 97 129 0 32 32.99 %
 Project 10 102 142 0 40 39.22 %