SOLUTION | AMS | TMS | APD | DPD | METHOD | TYPE | EF | CT | EXP | DL |
---|---|---|---|---|---|---|---|---|---|---|
Lopez-Paredes/Pajares/VillafaƱez - 2014-06-24 | 137.6 | 193 | 38.8 | 24.8676 | PSGSMINSLK | C | 0 | 0 | n/a |
|
Comment by author: Priority Rule - Minimum Activity Total Slack |
PROJECT | CPD | MS | SD | PD | RG | CPD & MS | DOWNLOAD | |
---|---|---|---|---|---|---|---|---|
Project 1 | 85 | 110 | 0 | 25 | 29.41 % |
|
||
Project 2 | 71 | 86 | 0 | 15 | 21.13 % |
|
||
Project 3 | 114 | 180 | 0 | 66 | 57.89 % |
|
||
Project 4 | 116 | 193 | 0 | 77 | 66.38 % |
|
||
Project 5 | 105 | 181 | 0 | 76 | 72.38 % |
|
||
Project 6 | 102 | 122 | 0 | 20 | 19.61 % |
|
||
Project 7 | 102 | 120 | 0 | 18 | 17.65 % |
|
||
Project 8 | 94 | 113 | 0 | 19 | 20.21 % |
|
||
Project 9 | 97 | 129 | 0 | 32 | 32.99 % |
|
||
Project 10 | 102 | 142 | 0 | 40 | 39.22 % |
|