Login E-Mail: Password: Forgot your Password? Register  
 Ranking & Analysis > Problem: mp_j120_a10_nr5_AgentCopp9 > Solution: 3878
.: Analysis   < previous  next >
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-24 129.4 184 40.1 23.2926 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 94 109 0 15 15.96 %
 Project 2 85 104 0 19 22.35 %
 Project 3 70 86 0 16 22.86 %
 Project 4 83 140 0 57 68.67 %
 Project 5 72 141 0 69 95.83 %
 Project 6 105 137 0 32 30.48 %
 Project 7 91 144 0 53 58.24 %
 Project 8 107 184 0 77 71.96 %
 Project 9 87 105 0 18 20.69 %
 Project 10 99 144 0 45 45.45 %