 Ranking & Analysis > Problem: mp_j120_a10_nr5_AgentCopp8 > Solution: 3874
.: Analysis   < previous  next >
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-24 157.7 174 57.8 14.4207 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 77 127 0 50 64.94 %
 Project 2 88 124 0 36 40.91 %
 Project 3 91 156 0 65 71.43 %
 Project 4 108 167 0 59 54.63 %
 Project 5 115 174 0 59 51.30 %
 Project 6 100 174 0 74 74.00 %
 Project 7 87 171 0 84 96.55 %
 Project 8 102 159 0 57 55.88 %
 Project 9 103 157 0 54 52.43 %
 Project 10 128 168 0 40 31.25 %