 Ranking & Analysis > Problem: mp_j120_a10_nr5_AgentCopp7 > Solution: 3873
.: Analysis   < previous  next >
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-24 133 151 42.1 8.53034 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 99 131 0 32 32.32 %
 Project 2 79 110 0 31 39.24 %
 Project 3 88 118 0 30 34.09 %
 Project 4 96 151 0 55 57.29 %
 Project 5 89 136 0 47 52.81 %
 Project 6 88 131 0 43 48.86 %
 Project 7 96 141 0 45 46.88 %
 Project 8 91 142 0 51 56.04 %
 Project 9 95 138 0 43 45.26 %
 Project 10 88 132 0 44 50.00 %