Login E-Mail: Password: Forgot your Password? Register  
 Ranking & Analysis > Problem: mp_j120_a10_nr5_AgentCopp7 > Solution: 3871
.: Analysis   < previous  next >
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-24 129.7 143 38.8 13.4973 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 99 120 0 21 21.21 %
 Project 2 79 109 0 30 37.97 %
 Project 3 88 101 0 13 14.77 %
 Project 4 96 142 0 46 47.92 %
 Project 5 89 133 0 44 49.44 %
 Project 6 88 129 0 41 46.59 %
 Project 7 96 135 0 39 40.63 %
 Project 8 91 142 0 51 56.04 %
 Project 9 95 143 0 48 50.53 %
 Project 10 88 143 0 55 62.50 %