MPSP Information | Download Problems | Upload Your Solution | Ranking & Analysis | Experiments | Contact Us |
.: Analysis | < previous next > |
SOLUTION | AMS | TMS | APD | DPD | METHOD | TYPE | EF | CT | EXP | DL |
---|---|---|---|---|---|---|---|---|---|---|
Lopez-Paredes/Pajares/VillafaƱez - 2014-06-24 | 129.7 | 143 | 38.8 | 13.4973 | PSGSMINSLK | C | 0 | 0 | n/a |
|
Comment by author: Priority Rule - Minimum Activity Total Slack |
PROJECT | CPD | MS | SD | PD | RG | CPD & MS | DOWNLOAD | |
---|---|---|---|---|---|---|---|---|
Project 1 | 99 | 120 | 0 | 21 | 21.21 % |
|
||
Project 2 | 79 | 109 | 0 | 30 | 37.97 % |
|
||
Project 3 | 88 | 101 | 0 | 13 | 14.77 % |
|
||
Project 4 | 96 | 142 | 0 | 46 | 47.92 % |
|
||
Project 5 | 89 | 133 | 0 | 44 | 49.44 % |
|
||
Project 6 | 88 | 129 | 0 | 41 | 46.59 % |
|
||
Project 7 | 96 | 135 | 0 | 39 | 40.63 % |
|
||
Project 8 | 91 | 142 | 0 | 51 | 56.04 % |
|
||
Project 9 | 95 | 143 | 0 | 48 | 50.53 % |
|
||
Project 10 | 88 | 143 | 0 | 55 | 62.50 % |
|