 Ranking & Analysis > Problem: mp_j120_a10_nr5_AgentCopp6 > Solution: 3870
.: Analysis   < previous  next >
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-24 293.5 393 203.4 88.8022 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 73 216 0 143 195.89 %
 Project 2 74 393 0 319 431.08 %
 Project 3 68 385 0 317 466.18 %
 Project 4 89 379 15 290 325.84 %
 Project 5 100 174 0 74 74.00 %
 Project 6 104 221 0 117 112.50 %
 Project 7 117 261 0 144 123.08 %
 Project 8 96 324 0 228 237.50 %
 Project 9 97 247 0 150 154.64 %
 Project 10 83 335 0 252 303.61 %