.: Analysis | < previous next > |
SOLUTION | AMS | TMS | APD | DPD | METHOD | TYPE | EF | CT | EXP | DL |
---|---|---|---|---|---|---|---|---|---|---|
Lopez-Paredes/Pajares/VillafaƱez - 2014-06-24 | 244.1 | 430 | 145.3 | 102.368 | PSGSMINSLK | C | 0 | 0 | n/a |
|
Comment by author: Priority Rule - Minimum Activity Total Slack |
PROJECT | CPD | MS | SD | PD | RG | CPD & MS | DOWNLOAD | |
---|---|---|---|---|---|---|---|---|
Project 1 | 85 | 139 | 0 | 54 | 63.53 % |
|
||
Project 2 | 71 | 124 | 0 | 53 | 74.65 % |
|
||
Project 3 | 114 | 377 | 0 | 263 | 230.70 % |
|
||
Project 4 | 116 | 425 | 0 | 309 | 266.38 % |
|
||
Project 5 | 105 | 359 | 6 | 254 | 241.91 % |
|
||
Project 6 | 102 | 162 | 0 | 60 | 58.82 % |
|
||
Project 7 | 102 | 161 | 0 | 59 | 57.84 % |
|
||
Project 8 | 94 | 149 | 1 | 55 | 58.51 % |
|
||
Project 9 | 97 | 253 | 5 | 156 | 160.83 % |
|
||
Project 10 | 102 | 292 | 3 | 190 | 186.28 % |
|