 Ranking & Analysis > Problem: mp_j120_a10_nr5_AgentCopp5 > Solution: 3866
.: Analysis   < previous  next >
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-24 244.1 430 145.3 102.368 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 85 139 0 54 63.53 %
 Project 2 71 124 0 53 74.65 %
 Project 3 114 377 0 263 230.70 %
 Project 4 116 425 0 309 266.38 %
 Project 5 105 359 6 254 241.91 %
 Project 6 102 162 0 60 58.82 %
 Project 7 102 161 0 59 57.84 %
 Project 8 94 149 1 55 58.51 %
 Project 9 97 253 5 156 160.83 %
 Project 10 102 292 3 190 186.28 %