.: Analysis |
SOLUTION | AMS | TMS | APD | DPD | METHOD | TYPE | EF | CT | EXP | DL |
---|---|---|---|---|---|---|---|---|---|---|
Lopez-Paredes/Pajares/VillafaƱez - 2014-06-24 | 255.1 | 399 | 156.3 | 101.793 | PSGSMINSLK | C | 0 | 0 | n/a |
|
Comment by author: Priority Rule - Minimum Activity Total Slack |
PROJECT | CPD | MS | SD | PD | RG | CPD & MS | DOWNLOAD | |
---|---|---|---|---|---|---|---|---|
Project 1 | 85 | 144 | 0 | 59 | 69.41 % |
|
||
Project 2 | 71 | 119 | 0 | 48 | 67.61 % |
|
||
Project 3 | 114 | 393 | 0 | 279 | 244.74 % |
|
||
Project 4 | 116 | 394 | 0 | 278 | 239.66 % |
|
||
Project 5 | 105 | 384 | 4 | 279 | 265.71 % |
|
||
Project 6 | 102 | 172 | 1 | 70 | 68.63 % |
|
||
Project 7 | 102 | 173 | 0 | 71 | 69.61 % |
|
||
Project 8 | 94 | 163 | 1 | 69 | 73.40 % |
|
||
Project 9 | 97 | 307 | 5 | 210 | 216.50 % |
|
||
Project 10 | 102 | 302 | 3 | 200 | 196.08 % |
|