Login E-Mail: Password: Forgot your Password? Register  
 Ranking & Analysis > Problem: mp_j120_a10_nr5_AgentCopp4 > Solution: 3863
.: Analysis
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-24 276.8 436 187.5 107.991 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 94 151 0 57 60.64 %
 Project 2 85 142 0 57 67.06 %
 Project 3 70 131 0 61 87.14 %
 Project 4 83 345 0 262 315.66 %
 Project 5 72 336 2 264 366.67 %
 Project 6 105 342 0 237 225.71 %
 Project 7 91 385 0 294 323.08 %
 Project 8 107 421 38 314 293.46 %
 Project 9 87 172 1 85 97.70 %
 Project 10 99 343 2 244 246.47 %