.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-24 386.3 478 286.4 63.8926 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 77 298 0 221 287.01 %
 Project 2 88 326 0 238 270.46 %
 Project 3 91 404 0 313 343.96 %
 Project 4 108 454 0 346 320.37 %
 Project 5 115 426 2 311 270.44 %
 Project 6 100 468 4 368 368.00 %
 Project 7 87 458 3 371 426.44 %
 Project 8 102 293 0 191 187.26 %
 Project 9 103 360 0 257 249.52 %
 Project 10 128 376 0 248 193.75 %