Login E-Mail: Password: Forgot your Password? Register  
 Ranking & Analysis > Problem: mp_j120_a10_nr5_AgentCopp2 > Solution: 3857
.: Analysis   < previous  next >
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-24 266.4 412 175.5 96.4932 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 99 140 0 41 41.41 %
 Project 2 79 167 0 88 111.39 %
 Project 3 88 143 0 55 62.50 %
 Project 4 96 264 0 168 175.00 %
 Project 5 89 203 0 114 128.09 %
 Project 6 88 284 0 196 222.73 %
 Project 7 96 397 0 301 313.54 %
 Project 8 91 352 3 261 286.81 %
 Project 9 95 363 0 268 282.11 %
 Project 10 88 351 3 263 298.86 %