MPSP Information | Download Problems | Upload Your Solution | Ranking & Analysis | Experiments | Contact Us |
.: Analysis | < previous next > |
SOLUTION | AMS | TMS | APD | DPD | METHOD | TYPE | EF | CT | EXP | DL |
---|---|---|---|---|---|---|---|---|---|---|
Lopez-Paredes/Pajares/VillafaƱez - 2014-06-24 | 266.4 | 412 | 175.5 | 96.4932 | PSGSMINSLK | C | 0 | 0 | n/a |
|
Comment by author: Priority Rule - Minimum Activity Total Slack |
PROJECT | CPD | MS | SD | PD | RG | CPD & MS | DOWNLOAD | |
---|---|---|---|---|---|---|---|---|
Project 1 | 99 | 140 | 0 | 41 | 41.41 % |
|
||
Project 2 | 79 | 167 | 0 | 88 | 111.39 % |
|
||
Project 3 | 88 | 143 | 0 | 55 | 62.50 % |
|
||
Project 4 | 96 | 264 | 0 | 168 | 175.00 % |
|
||
Project 5 | 89 | 203 | 0 | 114 | 128.09 % |
|
||
Project 6 | 88 | 284 | 0 | 196 | 222.73 % |
|
||
Project 7 | 96 | 397 | 0 | 301 | 313.54 % |
|
||
Project 8 | 91 | 352 | 3 | 261 | 286.81 % |
|
||
Project 9 | 95 | 363 | 0 | 268 | 282.11 % |
|
||
Project 10 | 88 | 351 | 3 | 263 | 298.86 % |
|