Login E-Mail: Password: Forgot your Password? Register  
 Ranking & Analysis > Problem: mp_j120_a10_nr5_AgentCopp2 > Solution: 3856
.: Analysis   < previous  next >
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-24 293 379 202.1 97.2071 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 99 155 0 56 56.57 %
 Project 2 79 151 0 72 91.14 %
 Project 3 88 146 0 58 65.91 %
 Project 4 96 370 0 274 285.42 %
 Project 5 89 331 0 242 271.91 %
 Project 6 88 340 0 252 286.36 %
 Project 7 96 364 0 268 279.17 %
 Project 8 91 356 2 265 291.21 %
 Project 9 95 358 3 263 276.84 %
 Project 10 88 359 2 271 307.96 %