 Ranking & Analysis > Problem: mp_j120_a10_nr5_AgentCopp1 > Solution: 3855
.: Analysis   < previous  next >
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-24 590.1 776 505.4 150.688 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 65 330 0 265 407.69 %
 Project 2 78 733 0 655 839.74 %
 Project 3 90 713 0 623 692.22 %
 Project 4 86 380 0 294 341.86 %
 Project 5 80 640 0 560 700.00 %
 Project 6 83 708 6 625 753.01 %
 Project 7 91 432 2 341 374.73 %
 Project 8 97 595 8 498 513.40 %
 Project 9 91 639 11 548 602.20 %
 Project 10 86 731 118 645 750.00 %