 Ranking & Analysis > Problem: mp_j120_a5_nr5_AgentCopp10 > Solution: 3850
.: Analysis   < previous  next >
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-24 429.4 628 331.2 241.978 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 85 175 6 90 105.88 %
 Project 2 71 115 0 44 61.97 %
 Project 3 114 604 16 490 429.83 %
 Project 4 116 628 0 512 441.38 %
 Project 5 105 625 0 520 495.24 %