 Ranking & Analysis > Problem: mp_j120_a5_nr5_AgentCopp3 > Solution: 3830
.: Analysis
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-23 455.2 536 359.4 65.9075 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 77 367 0 290 376.62 %
 Project 2 88 380 0 292 331.82 %
 Project 3 91 521 10 430 472.53 %
 Project 4 108 521 18 413 382.41 %
 Project 5 115 487 3 372 323.48 %