 Ranking & Analysis > Problem: mp_j90_a10_nr5_AgentCopp10 > Solution: 3765
.: Analysis   < previous  next >
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-23 163.2 186 96.2 14.3357 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 67 151 0 84 125.37 %
 Project 2 67 172 0 105 156.72 %
 Project 3 67 165 0 98 146.27 %
 Project 4 67 186 0 119 177.61 %
 Project 5 67 134 0 67 100.00 %
 Project 6 67 169 0 102 152.24 %
 Project 7 67 154 0 87 129.85 %
 Project 8 67 174 0 107 159.70 %
 Project 9 67 166 0 99 147.76 %
 Project 10 67 161 0 94 140.30 %