 Ranking & Analysis > Problem: mp_j90_a10_nr5_AgentCopp7 > Solution: 3756
.: Analysis   < previous  next >
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-23 294.7 399 214.1 110.479 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 74 399 4 325 439.19 %
 Project 2 81 384 0 303 374.07 %
 Project 3 94 265 3 171 181.92 %
 Project 4 77 327 0 250 324.68 %
 Project 5 75 192 0 117 156.00 %
 Project 6 78 124 0 46 58.97 %
 Project 7 76 360 0 284 373.68 %
 Project 8 82 399 0 317 386.59 %
 Project 9 87 370 0 283 325.29 %
 Project 10 82 127 0 45 54.88 %