.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-23 562.9 700 479 122.903 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 89 593 3 504 566.29 %
 Project 2 79 539 0 460 582.28 %
 Project 3 77 639 19 562 729.87 %
 Project 4 79 578 0 499 631.65 %
 Project 5 89 699 0 610 685.39 %
 Project 6 61 250 0 189 309.84 %
 Project 7 85 500 0 415 488.24 %
 Project 8 96 622 2 526 547.92 %
 Project 9 91 509 0 418 459.34 %
 Project 10 93 700 0 607 652.69 %