 Ranking & Analysis > Problem: mp_j90_a10_nr5_AgentCopp6 > Solution: 3753
.: Analysis   < previous  next >
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-23 519.7 701 435.8 158.705 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 89 564 0 475 533.71 %
 Project 2 79 384 0 305 386.08 %
 Project 3 77 678 0 601 780.52 %
 Project 4 79 518 10 439 555.70 %
 Project 5 89 658 18 569 639.33 %
 Project 6 61 143 0 82 134.43 %
 Project 7 85 562 0 477 561.18 %
 Project 8 96 452 0 356 370.83 %
 Project 9 91 537 0 446 490.11 %
 Project 10 93 701 3 608 653.76 %