Login E-Mail: Password: Forgot your Password? Register  
 Ranking & Analysis > Problem: mp_j90_a10_nr5_AgentCopp5 > Solution: 3751
.: Analysis
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-23 325.8 385 258.8 13.7744 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 67 338 0 271 404.48 %
 Project 2 67 315 0 248 370.15 %
 Project 3 67 323 0 256 382.09 %
 Project 4 67 326 0 259 386.57 %
 Project 5 67 332 0 265 395.52 %
 Project 6 67 322 0 255 380.60 %
 Project 7 67 355 0 288 429.85 %
 Project 8 67 326 0 259 386.57 %
 Project 9 67 316 0 249 371.64 %
 Project 10 67 305 1 238 355.22 %