 Ranking & Analysis > Problem: mp_j90_a10_nr5_AgentCopp3 > Solution: 3743
.: Analysis   < previous  next >
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-23 193.7 269 103.9 44.849 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 86 148 0 62 72.09 %
 Project 2 82 262 0 180 219.51 %
 Project 3 78 165 0 87 111.54 %
 Project 4 83 153 0 70 84.34 %
 Project 5 83 240 0 157 189.16 %
 Project 6 105 198 2 93 88.57 %
 Project 7 97 239 0 142 146.39 %
 Project 8 109 165 0 56 51.38 %
 Project 9 90 220 3 130 144.44 %
 Project 10 85 147 0 62 72.94 %