MPSP Information | Download Problems | Upload Your Solution | Ranking & Analysis | Experiments | Contact Us |
.: Analysis | < previous next > |
SOLUTION | AMS | TMS | APD | DPD | METHOD | TYPE | EF | CT | EXP | DL |
---|---|---|---|---|---|---|---|---|---|---|
Lopez-Paredes/Pajares/VillafaƱez - 2014-06-23 | 193.7 | 269 | 103.9 | 44.849 | PSGSMINSLK | C | 0 | 0 | n/a |
|
Comment by author: Priority Rule - Minimum Activity Total Slack |
PROJECT | CPD | MS | SD | PD | RG | CPD & MS | DOWNLOAD | |
---|---|---|---|---|---|---|---|---|
Project 1 | 86 | 148 | 0 | 62 | 72.09 % |
|
||
Project 2 | 82 | 262 | 0 | 180 | 219.51 % |
|
||
Project 3 | 78 | 165 | 0 | 87 | 111.54 % |
|
||
Project 4 | 83 | 153 | 0 | 70 | 84.34 % |
|
||
Project 5 | 83 | 240 | 0 | 157 | 189.16 % |
|
||
Project 6 | 105 | 198 | 2 | 93 | 88.57 % |
|
||
Project 7 | 97 | 239 | 0 | 142 | 146.39 % |
|
||
Project 8 | 109 | 165 | 0 | 56 | 51.38 % |
|
||
Project 9 | 90 | 220 | 3 | 130 | 144.44 % |
|
||
Project 10 | 85 | 147 | 0 | 62 | 72.94 % |
|