.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-23 530 689 446.1 143.224 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 89 523 0 434 487.64 %
 Project 2 79 402 0 323 408.86 %
 Project 3 77 674 1 597 775.33 %
 Project 4 79 564 5 485 613.92 %
 Project 5 89 668 73 579 650.56 %
 Project 6 61 182 0 121 198.36 %
 Project 7 85 601 5 516 607.06 %
 Project 8 96 574 0 478 497.92 %
 Project 9 91 468 0 377 414.29 %
 Project 10 93 644 4 551 592.47 %