 Ranking & Analysis > Problem: mp_j90_a10_nr5_AgentCopp1 > Solution: 3734
.: Analysis   < previous  next >
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-23 507 704 423.1 125.312 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 89 442 0 353 396.63 %
 Project 2 79 353 0 274 346.84 %
 Project 3 77 607 1 530 688.31 %
 Project 4 79 513 4 434 549.37 %
 Project 5 89 659 3 570 640.45 %
 Project 6 61 240 0 179 293.44 %
 Project 7 85 530 4 445 523.53 %
 Project 8 96 535 2 439 457.29 %
 Project 9 91 532 0 441 484.62 %
 Project 10 93 659 65 566 608.60 %