.: Analysis |
SOLUTION | AMS | TMS | APD | DPD | METHOD | TYPE | EF | CT | EXP | DL |
---|---|---|---|---|---|---|---|---|---|---|
Lopez-Paredes/Pajares/VillafaƱez - 2014-06-23 | 507 | 704 | 423.1 | 125.312 | PSGSMINSLK | C | 0 | 0 | n/a |
|
Comment by author: Priority Rule - Minimum Activity Total Slack |
PROJECT | CPD | MS | SD | PD | RG | CPD & MS | DOWNLOAD | |
---|---|---|---|---|---|---|---|---|
Project 1 | 89 | 442 | 0 | 353 | 396.63 % |
|
||
Project 2 | 79 | 353 | 0 | 274 | 346.84 % |
|
||
Project 3 | 77 | 607 | 1 | 530 | 688.31 % |
|
||
Project 4 | 79 | 513 | 4 | 434 | 549.37 % |
|
||
Project 5 | 89 | 659 | 3 | 570 | 640.45 % |
|
||
Project 6 | 61 | 240 | 0 | 179 | 293.44 % |
|
||
Project 7 | 85 | 530 | 4 | 445 | 523.53 % |
|
||
Project 8 | 96 | 535 | 2 | 439 | 457.29 % |
|
||
Project 9 | 91 | 532 | 0 | 441 | 484.62 % |
|
||
Project 10 | 93 | 659 | 65 | 566 | 608.60 % |
|