 Ranking & Analysis > Problem: mp_j90_a5_nr5_AgentCopp9 > Solution: 3729
.: Analysis   < previous  next >
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-23 800.6 864 726.6 79.9831 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 74 834 0 760 1027.03 %
 Project 2 74 673 0 599 809.46 %
 Project 3 74 773 0 699 944.60 %
 Project 4 74 859 8 785 1060.81 %
 Project 5 74 864 4 790 1067.57 %