Login E-Mail: Password: Forgot your Password? Register  
 Ranking & Analysis > Problem: mp_j90_a5_nr5_AgentCopp7 > Solution: 3724
.: Analysis   < previous  next >
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-23 555.6 646 475.4 81.8126 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 74 631 32 557 752.70 %
 Project 2 81 646 0 565 697.53 %
 Project 3 94 474 26 380 404.26 %
 Project 4 77 507 0 430 558.44 %
 Project 5 75 520 0 445 593.33 %