Login E-Mail: Password: Forgot your Password? Register  
 Ranking & Analysis > Problem: mp_j90_a5_nr5_AgentCopp7 > Solution: 3722
.: Analysis   < previous  next >
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-23 548.4 632 468.2 112.346 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 74 630 6 556 751.35 %
 Project 2 81 632 0 551 680.25 %
 Project 3 94 505 0 411 437.23 %
 Project 4 77 603 0 526 683.12 %
 Project 5 75 372 0 297 396.00 %