Login E-Mail: Password: Forgot your Password? Register  
 Ranking & Analysis > Problem: mp_j90_a5_nr5_AgentCopp5 > Solution: 3717
.: Analysis   < previous  next >
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-23 234.6 266 167.6 33.6719 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 67 262 0 195 291.05 %
 Project 2 67 241 0 174 259.70 %
 Project 3 67 176 0 109 162.69 %
 Project 4 67 248 0 181 270.15 %
 Project 5 67 246 0 179 267.16 %