SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-23 267 341 184.6 64.1155 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 86 195 0 109 126.74 %
 Project 2 82 334 10 252 307.32 %
 Project 3 78 206 0 128 164.10 %
 Project 4 83 279 3 196 236.15 %
 Project 5 83 321 0 238 286.75 %