 Ranking & Analysis > Problem: mp_j90_a5_nr5_AgentCopp2 > Solution: 3709
.: Analysis   < previous  next >
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-23 587.8 643 507.6 57.1734 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 74 643 0 569 768.92 %
 Project 2 81 633 3 552 681.48 %
 Project 3 94 547 9 453 481.92 %
 Project 4 77 598 0 521 676.62 %
 Project 5 75 518 3 443 590.67 %