SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-23 565 633 484.8 68.5069 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 74 633 0 559 755.41 %
 Project 2 81 615 0 534 659.26 %
 Project 3 94 499 4 405 430.85 %
 Project 4 77 582 0 505 655.84 %
 Project 5 75 496 0 421 561.33 %