 Ranking & Analysis > Problem: mp_j120_a20_nr5 > Solution: 3517
.: Analysis
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-20 130.1 192 30.6 12.6425 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 78 106 0 28 35.90 %
 Project 2 90 121 0 31 34.44 %
 Project 3 87 114 0 27 31.03 %
 Project 4 112 128 0 16 14.29 %
 Project 5 101 119 0 18 17.82 %
 Project 6 90 106 0 16 17.78 %
 Project 7 91 111 0 20 21.98 %
 Project 8 97 115 0 18 18.56 %
 Project 9 117 150 0 33 28.21 %
 Project 10 96 112 0 16 16.67 %
 Project 11 103 134 0 31 30.10 %
 Project 12 99 160 0 61 61.62 %
 Project 13 119 146 0 27 22.69 %
 Project 14 87 132 0 45 51.72 %
 Project 15 115 145 0 30 26.09 %
 Project 16 91 135 0 44 48.35 %
 Project 17 91 145 0 54 59.34 %
 Project 18 110 146 0 36 32.73 %
 Project 19 95 130 0 35 36.84 %
 Project 20 121 147 0 26 21.49 %