Login E-Mail: Password: Forgot your Password? Register  
 Ranking & Analysis > Problem: mp_j120_a20_nr5 > Solution: 3516
.: Analysis
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-20 129.9 189 30.4 11.2456 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Free Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 78 104 0 26 33.33 %
 Project 2 90 107 0 17 18.89 %
 Project 3 87 115 0 28 32.18 %
 Project 4 112 139 0 27 24.11 %
 Project 5 101 123 0 22 21.78 %
 Project 6 90 107 0 17 18.89 %
 Project 7 91 111 0 20 21.98 %
 Project 8 97 119 0 22 22.68 %
 Project 9 117 146 0 29 24.79 %
 Project 10 96 108 0 12 12.50 %
 Project 11 103 150 0 47 45.63 %
 Project 12 99 140 0 41 41.41 %
 Project 13 119 155 0 36 30.25 %
 Project 14 87 135 0 48 55.17 %
 Project 15 115 145 0 30 26.09 %
 Project 16 91 138 0 47 51.65 %
 Project 17 91 137 0 46 50.55 %
 Project 18 110 149 0 39 35.45 %
 Project 19 95 128 0 33 34.74 %
 Project 20 121 142 0 21 17.36 %