.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-20 144.7 228 45.35 12.4616 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Free Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 77 111 0 34 44.16 %
 Project 2 88 127 0 39 44.32 %
 Project 3 91 161 0 70 76.92 %
 Project 4 108 168 0 60 55.56 %
 Project 5 115 151 0 36 31.30 %
 Project 6 100 160 0 60 60.00 %
 Project 7 87 128 0 41 47.13 %
 Project 8 102 138 0 36 35.29 %
 Project 9 103 145 0 42 40.78 %
 Project 10 128 158 0 30 23.44 %
 Project 11 87 134 0 47 54.02 %
 Project 12 102 128 0 26 25.49 %
 Project 13 130 198 0 68 52.31 %
 Project 14 92 137 0 45 48.91 %
 Project 15 106 147 0 41 38.68 %
 Project 16 92 150 0 58 63.04 %
 Project 17 107 144 0 37 34.58 %
 Project 18 90 146 0 56 62.22 %
 Project 19 81 123 0 42 51.85 %
 Project 20 101 140 2 39 38.61 %