 Ranking & Analysis > Problem: mp_j120_a10_nr5 > Solution: 3478
.: Analysis   < previous  next >
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-20 450.5 486 341.7 13.3254 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Free Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 116 457 0 341 293.97 %
 Project 2 112 471 0 359 320.54 %
 Project 3 111 433 0 322 290.09 %
 Project 4 94 445 0 351 373.40 %
 Project 5 100 447 0 347 347.00 %
 Project 6 102 463 0 361 353.92 %
 Project 7 137 466 0 329 240.15 %
 Project 8 112 455 0 343 306.25 %
 Project 9 101 427 0 326 322.77 %
 Project 10 103 441 0 338 328.16 %