.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-20 450.4 481 341.6 20.2166 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Free Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 116 451 0 335 288.79 %
 Project 2 112 446 0 334 298.21 %
 Project 3 111 467 0 356 320.72 %
 Project 4 94 463 0 369 392.55 %
 Project 5 100 459 0 359 359.00 %
 Project 6 102 454 0 352 345.10 %
 Project 7 137 461 0 324 236.50 %
 Project 8 112 411 0 299 266.96 %
 Project 9 101 451 0 350 346.54 %
 Project 10 103 441 0 338 328.16 %