 Ranking & Analysis > Problem: mp_j120_a10_nr4 > Solution: 3473
.: Analysis   < previous  next >
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-20 343.7 389 246.7 5.57873 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Free Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 100 338 0 238 238.00 %
 Project 2 92 340 0 248 269.57 %
 Project 3 93 344 0 251 269.89 %
 Project 4 91 345 0 254 279.12 %
 Project 5 102 351 0 249 244.12 %
 Project 6 104 345 0 241 231.73 %
 Project 7 91 335 1 244 268.13 %
 Project 8 85 339 0 254 298.82 %
 Project 9 104 351 1 247 237.50 %
 Project 10 108 349 0 241 223.15 %