Login E-Mail: Password: Forgot your Password? Register  
 Ranking & Analysis > Problem: mp_j120_a10_nr4 > Solution: 3467
.: Analysis   < previous  next >
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-20 341 371 244 14.5067 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Free Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 100 326 0 226 226.00 %
 Project 2 92 346 0 254 276.09 %
 Project 3 93 348 0 255 274.19 %
 Project 4 91 356 0 265 291.21 %
 Project 5 102 345 0 243 238.24 %
 Project 6 104 346 0 242 232.69 %
 Project 7 91 349 1 258 283.52 %
 Project 8 85 328 2 243 285.88 %
 Project 9 104 339 0 235 225.96 %
 Project 10 108 327 0 219 202.78 %