.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-20 110.1 147 10.7 4.96767 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 100 104 0 4 4.00 %
 Project 2 102 122 0 20 19.61 %
 Project 3 107 113 0 6 5.61 %
 Project 4 93 105 0 12 12.90 %
 Project 5 94 112 0 18 19.15 %
 Project 6 106 114 0 8 7.55 %
 Project 7 98 109 0 11 11.22 %
 Project 8 105 115 0 10 9.52 %
 Project 9 91 100 0 9 9.89 %
 Project 10 98 107 0 9 9.18 %