 Ranking & Analysis > Problem: mp_j120_a10_nr3 > Solution: 3462
.: Analysis
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-20 112.2 146 12.8 7.39068 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Free Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 100 109 0 9 9.00 %
 Project 2 102 120 0 18 17.65 %
 Project 3 107 125 0 18 16.82 %
 Project 4 93 111 0 18 19.35 %
 Project 5 94 122 0 28 29.79 %
 Project 6 106 113 0 7 6.60 %
 Project 7 98 108 0 10 10.20 %
 Project 8 105 113 0 8 7.62 %
 Project 9 91 95 0 4 4.40 %
 Project 10 98 106 0 8 8.16 %