 Ranking & Analysis > Problem: mp_j120_a10_nr2 > Solution: 3440
.: Analysis
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-20 188 271 97.1 37.5483 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 99 154 0 55 55.56 %
 Project 2 79 169 0 90 113.92 %
 Project 3 88 146 0 58 65.91 %
 Project 4 96 197 0 101 105.21 %
 Project 5 89 177 0 88 98.88 %
 Project 6 88 158 0 70 79.55 %
 Project 7 96 250 0 154 160.42 %
 Project 8 91 256 0 165 181.32 %
 Project 9 95 208 0 113 118.95 %
 Project 10 88 165 0 77 87.50 %