.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-20 187.8 273 96.9 36.9878 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Free Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 99 166 0 67 67.68 %
 Project 2 79 132 0 53 67.09 %
 Project 3 88 156 0 68 77.27 %
 Project 4 96 199 0 103 107.29 %
 Project 5 89 165 0 76 85.39 %
 Project 6 88 180 0 92 104.55 %
 Project 7 96 240 0 144 150.00 %
 Project 8 91 258 0 167 183.52 %
 Project 9 95 217 0 122 128.42 %
 Project 10 88 165 1 77 87.50 %