 Ranking & Analysis > Problem: mp_j120_a5_nr4 > Solution: 3417
.: Analysis
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-20 179 188 82.8 13.8636 PSGSMINSLK C 0 0
n/a
 
  Comment by author: Priority Rule - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 95 180 0 85 89.47 %
 Project 2 104 187 0 83 79.81 %
 Project 3 100 183 0 83 83.00 %
 Project 4 76 177 0 101 132.90 %
 Project 5 106 168 0 62 58.49 %