 Ranking & Analysis > Problem: mp_j30_a10_nr4 > Solution: 3250
.: Analysis
Below you get a detailed overview over solution . Move over the Project entries to highlight Agent in diagram.
Click here to show global resource distribution diagram.
.: Solution information
SOLUTION AMS help TMS help APD help DPD help METHOD TYPE help EF help CT help EXP help DL
Lopez-Paredes/Pajares/VillafaƱez  - 2014-06-19 93.4 153 42.7 12.1111 PSGSMINSLK C 0 0
n/a
 
  Comment by author: PR - Minimum Activity Total Slack

PROJECT CPD help MS help SD help PD help RG help CPD & MShelp DOWNLOAD
 Project 1 48 99 0 51 106.25 %
 Project 2 42 92 0 50 119.05 %
 Project 3 35 69 0 34 97.14 %
 Project 4 63 109 0 46 73.02 %
 Project 5 49 102 0 53 108.16 %
 Project 6 44 73 0 29 65.91 %
 Project 7 70 108 3 38 54.29 %
 Project 8 49 80 0 31 63.27 %
 Project 9 56 121 26 65 116.07 %
 Project 10 51 81 0 30 58.82 %