MPSP Information | Download Problems | Upload Your Solution | Ranking & Analysis | Experiments | Contact Us |
.: Analysis | < previous next > |
SOLUTION | AMS | TMS | APD | DPD | METHOD | TYPE | EF | CT | EXP | DL |
---|---|---|---|---|---|---|---|---|---|---|
Dietz/Homberger - 2008-05-16 | 343.8 | 370 | 269.8 | 13.2808 | RES | C | 0 | 0 | n/a |
|
Comment by author: Central method (evolutionary metaheuristic) published in: Homberger, J. 2007. A Multi-agent System for the Decentralized Resource-constrained Multi-project Scheduling Problem. International Transactions in Operational Research, 14(6): 565-589. |
PROJECT | CPD | MS | SD | PD | RG | CPD & MS | DOWNLOAD | |
---|---|---|---|---|---|---|---|---|
Project 1 | 74 | 361 | 0 | 287 | 387.84 % |
|
||
Project 2 | 74 | 356 | 0 | 282 | 381.08 % |
|
||
Project 3 | 74 | 356 | 0 | 282 | 381.08 % |
|
||
Project 4 | 74 | 349 | 0 | 275 | 371.62 % |
|
||
Project 5 | 74 | 347 | 0 | 273 | 368.92 % |
|
||
Project 6 | 74 | 338 | 0 | 264 | 356.76 % |
|
||
Project 7 | 74 | 337 | 0 | 263 | 355.41 % |
|
||
Project 8 | 74 | 328 | 0 | 254 | 343.24 % |
|
||
Project 9 | 74 | 329 | 0 | 255 | 344.60 % |
|
||
Project 10 | 74 | 322 | 0 | 248 | 335.14 % |
|
||
Project 11 | 74 | 364 | 0 | 290 | 391.89 % |
|
||
Project 12 | 74 | 363 | 0 | 289 | 390.54 % |
|
||
Project 13 | 74 | 355 | 0 | 281 | 379.73 % |
|
||
Project 14 | 74 | 353 | 0 | 279 | 377.03 % |
|
||
Project 15 | 74 | 349 | 0 | 275 | 371.62 % |
|
||
Project 16 | 74 | 341 | 0 | 267 | 360.81 % |
|
||
Project 17 | 74 | 340 | 0 | 266 | 359.46 % |
|
||
Project 18 | 74 | 333 | 0 | 259 | 350.00 % |
|
||
Project 19 | 74 | 330 | 0 | 256 | 345.95 % |
|
||
Project 20 | 74 | 325 | 0 | 251 | 339.19 % |
|